Storm Water Pollution Prevention Plan Review

Construction Stormwater General Permit (CSGP)As of December 18, 2021, Indiana no longer administers the construction stormwater program under Indiana Administration Code (327 IAC 15-5 or Rule 5). Permitting coverage is now issued under the Construction Stormwater General Permit (CSGP). CSGP is a performance-based regulation designed to reduce pollutants that are associated with construction and/or land disturbing activities.

Storm Water Pollution Prevention Plan (SWPPP)
SWPPP will need to be submitted to the Jennings County SWCD via hard copy and electronically. Fee payment is expected at the time of plan drop off. Be sure to include the project manager's name and phone number. If you have any questions regarding plan submittals, please email Becca McClellan or call (812) 346-3411 Ext. 3

Jennings County SWCD has 14 calendar days to review the submitted plans and either approve or request revisions AFTER review fee has been paid.

Once the SWPPP is approved by the SWCD the NOI (Notice of Intent) and IDEM filing fee can be submitted to IDEM. This permit is effective for 5 years and will need to be reviewed if the project surpasses 5 years.

Our review fee applies to ALL projects inside Jennings County limits.

Construction may begin 48 hours after submitting NOT.

image ►Construction/Land Disturbance Permitting Overview

image ►The Permitting Process

image Jennings County Soil & Water Conservation District
2600 North State Highway 7
North Vernon, IN 47265
(812) 346-3411 EXT. 3